Before you buy an inverter, understand your office load.
A practical checklist for choosing backup power around the equipment that matters.
Start with essential equipment
List the equipment that must operate during an outage. Separate essential loads from optional ones. Computers, network equipment, printers and cooling devices have different demand profiles.
Account for starting and peak loads
Nameplate ratings, measured consumption and starting demand all matter. Equipment such as printers or motors may need more capacity at particular moments than their usual running demand suggests.
Agree your target runtime
An inverter rating describes output capability; it does not alone tell you how many hours the system will run. Battery capacity, usable energy, losses and load determine runtime.
Plan the installation
Ask for an itemised scope covering protection devices, cabling, earthing, ventilation, mounting and commissioning. A site assessment helps identify installation constraints.
Think about support
Confirm equipment warranty, maintenance needs and who to contact when a fault occurs. Keep your equipment schedule and handover documentation.
Prepared by Anjos Technology. Your equipment and site conditions determine the right specification; request an assessment for project-specific advice.
All insightsMatch your backup to your actual loads
Size your backup power around the work that matters.
By Anjos Technology Limited · Updated 3 October 2026. Examples are illustrative; request a site-specific assessment.
Work in watts and watt-hours before shopping in kVA
Suppose the essential measured office load is 500 watts and the required runtime is four hours. The appliances need approximately 2 kilowatt-hours of AC energy. If, purely for illustration, usable battery fraction is 80% and inverter efficiency is 90%, nominal stored energy would need to be at least 2 ÷ (0.8 × 0.9), or about 2.78 kilowatt-hours before additional design allowances. This example is not an equipment recommendation or an Anjos project result.
Battery chemistry, allowable discharge, temperature, ageing, inverter idle demand and changing loads affect the actual result. Starting demand and power factor must also be checked against continuous and peak inverter ratings. A kVA label alone does not establish runtime. Measure representative use and have the proposed equipment checked against manufacturer limits.
Separate essential circuits
A printer, kettle or air conditioner added to the backup circuit can change both demand and runtime. Agree which loads belong on the system and label the circuits. Solar generation should be assessed against the site, shade, array design, weather and the battery charging requirement. Do not treat a panel nameplate as guaranteed energy available at every hour.
What the quotation and handover should show
A load schedule, target runtime and all sizing assumptions.
Model-specific inverter and battery ratings, warranties and operating limits.
Protection, earthing, suitable cables, ventilation and mounting in the installation scope.
Commissioning results, circuit labels and a practical operating guide.
A service contact, maintenance requirements and a fault-response scope.
Ask a competent installer to assess electrical work and the actual premises. Keep people away from exposed live connections and do not attempt internal inverter or battery repairs. For an enquiry, share the equipment list, outage pattern, location and required runtime; Anjos can then agree the assessment required.
Technical reference: Victron inverter selection guidance. Manufacturer examples do not establish brand accreditation or a particular installation specification.